Chartering operations technique

Stages of a chartering deal

The chartering process passes through seven consecutive stages — from the offer to the final settlement.

  1. Offer — the shipowner or broker offers a vessel: its characteristics (type, tonnage, speed, deadweight), the route (ports of loading/discharge) and the freight rate.
  2. Negotiations — the charterer clarifies the terms: price, laytime, demurrage, despatch; rates may be adjusted and special conditions discussed.
  3. Recap / Confirmation — written confirmation of the main terms, exchange of recaps between brokers, agreement of the details and the final consent of the parties.
  4. Charter Party Execution — signing of the contract, use of standard terms (GENCON, NYPE, etc.), calculation of freight and advances, determination of the date the vessel is ready.
  5. Mobilization — the vessel proceeds to the port of loading, cargo is prepared, documents are completed, port services are notified.
  6. Operations — loading and discharging of the cargo, laytime control, issuance of bills of lading.
  7. Settlement — invoicing, assessment of demurrage/despatch, final freight calculation, payments by all parties.

Typical stages of chartering correspondence

Stage 1: Offer

FROM: [Shipowner / Broker]
TO: [Charterer / Charterer's Broker]

OFFERING FOR PROMPT FIXTURE:

Vessel Name: MV EXAMPLE
Type: General Cargo / Container / Tanker
Class: [Classification Society]
DWT: [Deadweight Tonnage]
Bale Capacity: [cubic metres]
Speed: [knots]
Built: [year of build]
Flag: [flag]

TRADING: [trading area]

LOAD PORT(S): [ports of loading with dates]
DISCHARGE PORT(S): [ports of discharge]

FREIGHT: $[amount] per metric ton / per container / Lumpsum
PAYABLE: [method of payment]

LAYTIME: [days allowed for operations]
DEMURRAGE: $[amount] per day per port
DISPATCH: [% of freight for saving laytime]

CAN LOAD: [date the vessel is ready]
EARLIEST: [date of readiness]

GENERAL CONDITIONS: [GENCON / BALTIME / NYPE / etc.]

Validity: [period of validity of the offer, usually 24–48 hours]

Stage 2: Recap

RECAP — CONFIRMATION OF FIXTURE

FROM: [Charterer's Broker]
TO: [Shipowner's Broker]

REF: [offer number]
DATE: [recap date]

FIXTURE DETAILS:

VESSEL: MV EXAMPLE (as above)

CARGO: [description of cargo]
Quantity: [quantity in metric tonnes]
Package: [packaging]

LOAD PORT(S): [ports and dates]
DISCHARGE: [ports]

FREIGHT: $[amount] all-in [method of calculation]

PAYMENT TERMS: Bill of Lading terms / Prepaid / 1/2 on B/L, 1/2 on delivery

LAYTIME PROVISIONS:
- Laytime: [number of days]
- Time begins: [from what moment]
- Time stops: [when it stops]
- Demurrage: $[amount] per day per port or pro-rata
- Dispatch money: [% for saving]

GENERAL CONDITIONS: [standard conditions]

SPECIAL CLAUSES:
- [any additional conditions]

BOOKING REFERENCE: [booking reference]

OWNER'S CONFIRMATION: [date of the shipowner's confirmation]
CHARTERER'S CONFIRMATION: [date of the charterer's confirmation]

BROKERS: [brokers of the parties]

Stage 3: Recap Correction

RECAP CORRECTION / RELETTERING

TO AMEND RECAP DTD [date of the original recap]

PLEASE NOTE THE FOLLOWING AMENDMENTS:

ITEM 1: [what it was] SHOULD READ [how it should be]
ITEM 2: [what it was] SHOULD READ [how it should be]

ALL OTHER TERMS AS IN RECAP DATED [date]

PLEASE CONFIRM YOUR ACCEPTANCE OF ABOVE AMENDED TERMS

Key parameters of a chartering deal

Freight Rate

Type of rateDescriptionExample
Ad valorem% of the value of the cargo5% of the cargo value
Per metric tonFor each tonne of cargo$50/MT
Per tonPer tonne of the vessel's capacity$100/ton of the vessel
LumpsumA fixed sum per voyage regardless of the cargo$500,000 per voyage
Per TEU/FEUPer container unit$2,000 per TEU
Sliding scaleThe more cargo, the lower the rateVolume discount
Per diemHire rate per day (time charter)$50,000 per day

Laytime

Kind of daysDefinition
Running daysCalendar days (consecutive).
Working daysWorking days, excluding weekends.
Weather-working daysExcluding days of bad weather.
Excepted daysExcluded days: holidays, strikes.

Examples of formulations:

Demurrage and Despatch

Laytime is included in the cost of freight. Exceeding the limit entails demurrage, and early completion entails despatch (a bonus for saving time, usually 50% of the demurrage rate).

FORMULAS:

DEMURRAGE = Number of excess days × Daily demurrage rate

DISPATCH = Number of days saved × 50% × Demurrage rate

EXAMPLE (overrun):
- Laytime: 10 days
- Actually worked: 12 days
- Demurrage rate: $5,000/day
- DEMURRAGE = 2 days × $5,000 = $10,000

EXAMPLE (saving):
- Laytime: 10 days
- Actually worked: 8 days
- DISPATCH = 2 days × 50% × $5,000 = $5,000 (saving for the shipowner)

Typical charter-party terms (GENCON 94)

  1. Parties — the shipowner (Owner) and the charterer (Charterer).
  2. Vessel — name, type, class, deadweight (DWT), permitted ports.
  3. Cargo — description and quantity, packaging and marking, prohibited cargoes.
  4. Freight — amount and unit of calculation, method of payment (Bill of Lading terms, Prepaid), currency of payment.
  5. Laytime — number of days, kinds of days (running, working, weather-working), start of the count (ready, NOR), excluded days.
  6. Demurrage & Despatch — the rate for overrun, the percentage of freight for early completion.
  7. Port charges — who pays (Owner, Charterer, split), the amounts of the charges.
  8. Insurance — who insures the cargo, the amount of cover (usually 110% of the value).
  9. General Average — joint participation in the compensation of losses.
  10. Liability — exclusions from liability, limits of liability.
  11. Force Majeure — kinds of circumstances and their consequences.
  12. Dispute and arbitration — choice of law, arbitration (London, New York, etc.).

Examples of recaps with explanations

Example 1. Voyage charter for dry cargo

                    RECAP CONFIRMATION

DATE: 30 July 2026
REFERENCE: 2026/DC/001
VESSEL: MV NORTHERN STAR
TYPE: General Cargo Ship
DWT: 35,000 MT
FLAG: Panama
CLASS: Lloyd's Register + DNV

FROM: SHIPPER'S BROKER (Exporter)
TO: OWNER'S BROKER (Shipowner)

CARGO DESCRIPTION:
- Steel coils
- Quantity: 32,000 metric tons
- In 40 x 40 ft containers (800 containers total)
- Shipper: ABC Steel Mills, South Korea

LOAD PORT: Busan, South Korea
ETA: 10–15 August 2026
DISCHARGE PORT: Rotterdam, The Netherlands
ETA: 15–20 September 2026 (via Suez Canal)

FREIGHT RATE:
Base Freight: $18.50 per metric ton
Total Freight: 32,000 × $18.50 = $592,000
Currency: USD

PAYMENT TERMS:
- 50% on B/L signing: $296,000
- 50% on arrival: $296,000
- Payment method: Bank transfer

LAYTIME PROVISIONS:
- Loading laytime: 5 running days
- Discharging laytime: 5 running days
- Time commences: Upon notice of readiness (NOR)
- Time ceases: Upon completion of all cargo work

DEMURRAGE:
- $3,500 per day per port
- Pro-rata for part of day

DISPATCH MONEY:
- 50% of demurrage rate for each day saved
- Applicable if operations completed before laytime expires
- Example: 1 day saved = $1,750 dispatch

GENERAL CONDITIONS:
- GENCON 94
- Hague-Visby Rules apply
- All bills of lading to be clean

SPECIAL CLAUSES:
1. Both ports will revert at Owner's/Charterer's option
2. Cargo to be worked 24 hours per day if both parties agree
3. Gears to be used if available at no extra cost to Charterer
4. Owner's agent at load port to be nominated by shippers
5. All stevedoring to be in accordance with local regulations

INSURANCE:
- Charterer to arrange insurance at 110% of cargo value
- B/L to be marked "Freight prepaid"

VALIDITY OF OFFER: 48 hours from this date

OWNER'S BROKER: Nordic Shipping AS
Tel: +47 2223 4444, Email: broker@nordicship.no
CHARTERER'S BROKER: Global Trade Partners
Tel: +82 2 1234 5678, Email: bp@globalpartners.kr
ItemWhat it meansWhy it matters
ETA BusanThe vessel will be ready to load on 10–15 AugustThe charterer must have the cargo ready by that time
Freight $18.50/MTThe standard rate for Korean steel exportsIf the cargo does not fit the tonnage, the freight may change
50/50 paymentHalf on signing, half on arrivalThe shipowner is guaranteed at least half before delivery
5 days laytime5 days each for loading and dischargeDemurrage is paid from the 6th day
$3,500/day demurrage$3,500 is paid for each day of overrunExpensive — the charterer strives to finish on time
GENCON 94The standard terms of the international associationThe parties know their obligations without a detailed description
Gears to be usedThe ship's cranes are used free of chargeA saving for the charterer (usually $200–300/day)

Example 2. Tanker time charter

                    RECAP — TIME CHARTER

DATE: 5 August 2026
REFERENCE: 2026/TC/TANK/042

VESSEL: MT OCEAN PIONEER
Type: Crude Oil Tanker
Capacity: 130,000 metric tons (DWT)
Age: 5 years, Class: ABS + Nippon Kaiji Kyokai
Flag: Liberia
Speed: 14.5 knots loaded, 15 knots ballast

PERIOD: 36 months
EARLIEST DELIVERY: 15 September 2026
PLACE OF DELIVERY: Singapore (Seller's option between Singapore/Rotterdam)
PLACE OF REDELIVERY: Worldwide, normal trading limits

HIRE (DAILY RATE):
Base Rate: $48,000 USD per calendar day
Delivery to 25,000 bbls basis Suez passing = $48,000
- Full period, all risks for Charterer

PAYMENT:
- Monthly in advance on a fixed date
- Account payable: [Bank details]
- Currency: USD

CREW COSTS:
- Owner pays all crew costs
- Charterer reimburses Owner monthly for crew changes
- Estimated: $800/month per crew member

FUEL/BUNKERS:
- Charterer to pay all fuel and bunker costs
- Owner to provide clean ship; Charterer to settle all bunkering invoices
- Bunker sampling at load port and discharge port

MAINTENANCE:
- Owner responsible for hull and machinery maintenance
- Charterer responsible for cargo-related maintenance
- Vessel in "good and efficient" condition

INSURANCE:
- Owner to maintain P&I insurance (Protection & Indemnity)
- Charterer to arrange cargo insurance
- Owner's All Risks coverage at Charterer's expense

REDELIVERY:
- Vessel to be redelivered "in same good condition as delivered"
- With fuel (if time permits, seller to top off bunkers)
- Normal wear and tear excepted

OFF-HIRE CLAUSE:
- $900/day deduction from hire for each day of breakdown exceeding 24 hours
- Examples of off-hire events:
  * Machinery breakdown
  * Hull repairs
  * Defects affecting cargo operations

GENERAL CONDITIONS:
- SHELLTIME 4 (Tanker Time Charter Uniform Conditions)
- BIMCO Standard Form
- Hague-Visby Rules

SPECIAL PROVISIONS:
1. Charterer has options to extend for additional 12, 24, or 36 months
2. Early redelivery possible with 90 days' notice
3. Vessel capable of all ports worldwide except those restricted by draft
4. Charterer has right to substitute similar vessel with Owner's approval
5. War risk insurance to be arranged at Charterer's cost if required

PERFORMANCE BONDS:
- Charterer to provide performance bond = 3 months hire
- Amount: $144,000 (3 × $48,000)

DISPUTES:
- London Arbitration
- Two arbitrators + umpire
- LCIA Rules apply

VALIDITY: 48 hours from this date

Owner's Broker: Tanker Solutions Inc.
Tel: +1 212 555 0123
Charterer's Broker: Global Energy Logistics
Tel: +44 20 7123 4567
ItemWhat it meansWhy it matters
36 monthsThe vessel is chartered for 3 yearsA long-term commitment, stable income for the shipowner
$48,000/dayPayment of $48,000 every day for 3 yearsTotal: 48,000 × 365 × 3 ≈ $52.6m for the period
Delivery SingaporeThe vessel is delivered in Singapore (or Rotterdam)The charterer starts paying from that moment
Owner pays crewThe shipowner pays the crew's wagesThe charterer reimburses the costs on crew changes
Charterer pays fuelThe charterer pays for fuelThe shipowner saves on consumables
Off-hire clause$900 is deducted for each day of breakdown over 24 hoursMotivates keeping the vessel in good condition
Performance bondThe charterer deposits a $144,000 guaranteeInsurance for the shipowner against non-payment
SHELLTIME 4The standard terms of Shell tanker chartersThe parties know their rights and obligations precisely

Example 3. Container voyage charter

                RECAP — CONTAINER VOYAGE CHARTER

DATE: 12 August 2026
REFERENCE: 2026/CONT/SH/089

VESSEL: CONTAINER STAR EXPRESS
Type: Container Ship (Cellular)
Capacity: 5,400 TEU (20-foot equivalent units)
Speed: 23 knots
Gear: Gearless vessel
Flag: Hong Kong

TRADING:
Route: Asia — Europe
Load Port: Shanghai, China
Discharge Port: Rotterdam, The Netherlands

LOADING: CW 36-37, 2026 (Week 36-37 of 2026)
ETA Load: 2–8 September 2026
ETA Discharge: 2–8 October 2026 (via Suez)

FREIGHT RATE:
Base: $1,200 per TEU for full containers
Empty Container Cost: $200 per TEU (if repositioning required)
Reefer Surcharge: +15% (for refrigerated containers)
Total Estimated Freight:
- 4,000 Loaded TEU × $1,200 = $4,800,000
- 400 Empty TEU × $200 = $80,000
- 200 Reefer TEU (within the loaded) × 15% × $1,200 = $36,000
TOTAL: ~$4,916,000

PAYMENT TERMS:
- Payment due within 10 days of B/L date
- Advance: 25% before loading starts = $1,229,000
- Balance: 75% within 10 days of B/L = $3,687,000

LAYTIME:
- Loading: 5 days (included in freight)
- Discharging: 5 days (included in freight)
- Free time includes ship-to-shore (STS) cranes
- Additional days: $8,500 per day per port

DEMURRAGE:
- Port demurrage: $8,500 per day
- Container demurrage (after discharge):
  * 20-ft: $5 per day
  * 40-ft: $8 per day
- Free time: 7 days after discharge

DISPATCH BONUS:
- 50% of daily detention rate if loading/discharging completed early

GENERAL CONDITIONS:
- CONTINOLOAD terms (Container Voyage Charter Standard)
- Hague-Visby Rules
- Bills of Lading to be clean

WEIGHT LIMITATIONS:
- Maximum container weight: 30 MT per container
- Overweight surcharge: $200 per MT in excess of 20 MT
- Dangerous goods: IMDG Code compliance mandatory

SPECIAL CLAUSES:
1. Containers must be inspected and weighed at load port
2. Shipper responsible for accurate weight declaration
3. Heavy containers to be declared 14 days before loading
4. Reefer containers: Owner to provide power connection and monitoring
5. SOC (Shipper Owned Container) allowed: $75 per TEU additional fee
6. Vessel to call at Suez Canal pilots' station (on-hire)

CARGO INSURANCE:
- Shipper to arrange insurance at 110% CIF value
- B/L must state "Freight prepaid" or "Freight to pay" as per agreement

DOCUMENTATION:
- Shipper to provide shipping instructions 7 days before loading
- Container number, seal numbers, weights must be accurate
- Shipper liable for errors in documentation

STRIKES/FORCE MAJEURE:
- Strikes and lockouts: time on demurrage + hire continues
- War: time suspended, no demurrage/hire accrual
- Deviation: not payable unless forced by circumstances

REDELIVERY/RETURN:
- Empty containers must be returned within free time (7 days)
- Storage charge: $10 per container per day after free time
- Damaged containers: repaired at Owner's expense or charged to charterer

COMPLAINTS:
- Load port: must be filed within 72 hours of operations
- Discharge port: must be filed within 48 hours of discharge
- Later claims not accepted

VALIDITY: 36 hours from this date, then null and void unless extended

Owner's Broker: Coastal Shipping & Logistics
Tel: +852 2299 1234
Charterer's Broker: Sunrise Forwarding Ltd.
Tel: +8610 5555 6666
ItemWhat it meansWhy it matters
5,400 TEUThe vessel carries 5,400 twenty-foot containersMaximum capacity with 20-foot containers
$1,200/TEUThe standard Shanghai–Rotterdam rateDepends on demand, season and capacity
5 days laytime5 days each for loading and dischargeContainer operations are usually faster — 2–3 days
Empty container $200Payment for the carriage of empty containersTypical for routes with a cargo flow imbalance
Reefer surcharge +15%Refrigerated containers are more expensivePayment for higher energy consumption
$8,500/day additionalFor additional days beyond 5 days laytimeMotivates fast port work
Weight limitations 30 MTMaximum 30 tonnes per containerProtection against overloading, stability of the vessel
SOC containers $75The shipper's container instead of the vessel'sPermitted for an additional fee
Complaints 72/48 hoursClaims are filed within tight time limitsOtherwise the cargo is considered delivered in proper condition
Validity 36 hoursThe offer is valid for 36 hoursA fast-moving market requires promptness

Real example: a Contract of Affreightment (Gencon 94)

Below is a real example of a voyage charter party under the GENCON 94 form for the carriage of a consignment of steel by several bulk carriers. This is a classic Contract of Affreightment (COA) — a contract for a series of scheduled shipments, where several vessels and several lots of cargo fall under a single charter.

Part I — the completed "header" of the deal

RECOMMENDED UNIVERSAL CHARTER PARTY OF THE BALTIC AND INTERNATIONAL
MARITIME COUNCIL (REVISED IN 1922, 1976 AND 1994)
CODE NAME: "GENCON"

Place and date: Moscow, 24.05.2026

Owners: Shipping Ltd., Edinburgh, United Kingdom
Charterers: First class

Name of vessel / Gross-Net tonnage:
  m/v "BALTIC SKY" or substitute — 2061/1178
  m/v "SONATA" or substitute — 5184/3046

Total deadweight on summer load line (about):
  3,085 t — m/v "BALTIC SKY"
  7,909 t — m/v "SONATA"

Present position: in the course of a voyage
Expected readiness to load: see boxes 21 and 22

Port or place of loading / discharge:
  1 SP Rotterdam or Dunkirk → 1 SP Vyborg or St. Petersburg
  1 SP Vyborg or St. Petersburg or Ust-Luga → 1 SP Dordrecht
  1 SP Vyborg or St. Petersburg or Ust-Luga → 1 SP Rotterdam

Cargo: about 150,000 t of steel in total, stowage by weight,
  in lots of 2,800 – 6,000 t each, jointly agreed

Freight rate (FIOS L/S/D terms):
  Euro 12/t — Rotterdam
  Euro 13/t — Dunkirk
  Euro 36/t — Rotterdam
  Euro 25/t — Rotterdam

Payment of freight: 100% within 10 banking days of the date of signing
  and release of the bill of lading, to the owners' account (see box 23)

Loading/discharging gear: see box 24

Laytime for loading:
  1,500 t WWD SHINC
Laytime for discharging:
  1,500 t WWD SSHEX UU

Shippers: to be nominated on the charterers' instruction
Agents (loading/discharge): see box 34

Demurrage rate (per day, pro rata):
  Euro 3,000 — m/v "Baltic Sky"
  Euro 6,000 — m/v "Sonata" (see also box 26)

Cancelling date: see boxes 21 and 22
General average to be adjusted in: London

Tax on freight: for the charterers' account
Brokerage commission: no commission

Law and arbitration: London (see clause 19)

It is mutually agreed that this contract shall be performed subject to the
conditions of the charter party, which includes both Part I and Part II. In
the event of a conflict, the provisions of Part I prevail over those of Part II.

Part II — key terms of GENCON 94

The full standard terms of "Gencon 94" (Part II) include 19 clauses. The key ones are:

ClauseEssence
1. Presentation of the vesselThe vessel shall proceed to the port of loading after completing its previous obligations, load and deliver the cargo to the port of discharge.
2. Owners' liabilityLiability only in the absence of due diligence in making the vessel seaworthy; a list of exceptions (nautical fault, etc.).
3. DeviationThe vessel may call at any ports, tow, and deviate to save life and property.
4. Payment of freightFreight is paid on the loaded quantity; prepaid freight is deemed earned and non-returnable, even if the vessel/cargo is lost.
5. Loading/dischargingThe cargo is worked by the charterers free of the risk and expense of the owners (corresponds to FIOS); the provision of the vessel's cargo gear.
6. LaytimeLaytime runs from 13:00/14:00 if the notice is given before 12:00, otherwise from 06:00/08:00 the following working day; shifting to the berth and customs formalities are not counted as laytime.
7. DemurragePaid per day or pro rata; on non-payment — a 96-hour notice, then the right to cancel the charter.
8. LienThe owners have a lien on the cargo and sub-freight as security for freight, dead freight, demurrage and losses.
9. CancellingIf the vessel is not ready by the cancelling date, the charterer may cancel the charter; the owners must give notice of the delay and offer a new date.
10. Bills of ladingSigned in the "Congenbill 1994" form with the note "Without prejudice to this charter party".
12. General averageAdjusted in London under the York-Antwerp Rules 1994.
15. Brokerage commissionCharged on earned freight, dead freight and demurrage; on non-performance — 1/3 of the commission in favour of the brokers.
16. General strike clauseThe rights of the parties in strikes/lockouts affecting loading or discharge.
17. War risks ("Voywar 1993")The owners' right to cancel the contract or deviate from the route in the event of war risks (war, mines, piracy, terrorism, blockade).
18. General ice clauseThe master's right to leave the port in case of ice danger; the charterer's rights when the port of discharge is inaccessible.
19. Law and arbitrationSubject to English law, arbitration in London (or another option — New York / an agreed place).
What is important in this example: this is a COA (Contract of Affreightment) — a contract for a series of shipments of steel (~150,000 t) by several substitute vessels ("Baltic Sky", "Sonata") with flexible ports of loading/discharge and separate freight rates by direction. The FIOS L/S/D terms mean that loading/discharging and stowage are performed at the charterer's expense and risk — typical for bulk cargo. Laytime is set at a rate of 1,500 t/day with different counting regimes: for loading — WWD SHINC, for discharge — WWD SSHEX UU.

Peculiarities of correspondence and standard expressions

Phrases in chartering correspondence

SituationEnglish expressionTranslation
On offerWe are offering…We are offering…
For your prompt fixture…For your prompt fixture…
Subject to owner's approval…Subject to owner's approval…
Validity of 48 hours…Validity of 48 hours…
In negotiationsWe are a bit high at this level…This is a bit expensive…
Can you reduce the rate?Can you reduce the rate?
We are more at…We are closer to [an amount]…
This is our rock bottom…This is our rock bottom…
Let us come back to you…We will get back to you…
On recapAs per recap dated…As per recap dated…
Please confirm…Please confirm…
We hereby confirm…We hereby confirm…
Subject toSubject to…
All other terms as previously agreedAll other terms as previously agreed
On reference to conditionsUnder the General Conditions…Under the General Conditions…
According to the Charter Party…According to the Charter Party…
As per Clause…As per Clause…

Typical sequence of correspondence

DAY 1, 09:00 — OFFER from the shipowner

From: Owner's Broker
To: Charterer's Broker
Subject: OFFERING MV EXAMPLE

Dear Sirs,

We are offering for your prompt fixture:

VESSEL: MV EXAMPLE
DWT: 35,000 MT
CAN LOAD: 15–20 August
LOAD: Shanghai
DISCHARGE: Rotterdam
FREIGHT: $18.50/MT
LAYTIME: 5 running days each port
DEMURRAGE: $3,500 per day
DISPATCH: 50%
GENERAL CONDITIONS: GENCON 94

Please advise your interest.

Best regards,
Owner's Broker

────────────────────────────────

DAY 1, 10:30 — CLARIFYING QUESTION

From: Charterer's Broker
To: Owner's Broker
Subject: RE: OFFERING MV EXAMPLE

Thanks for the offer.

We are interested but have some questions:

1. What's the earliest you can adjust your freight level?
2. Can you accept 7 days laying days?
3. Who pays stevedoring?

Please advise.

────────────────────────────────

DAY 1, 11:45 — REPLY TO QUESTIONS

From: Owner's Broker
To: Charterer's Broker
Subject: RE: RE: OFFERING MV EXAMPLE

Regarding your questions:

1. Freight: We can consider $18.00/MT but no further reduction.
2. Laytime: 5 days is our limit as per other commitments.
3. Stevedoring: All in cost, included in freight.

Please confirm if acceptable.

────────────────────────────────

DAY 1, 14:00 — CONSENT

From: Charterer's Broker
To: Owner's Broker
Subject: RECAP — MV EXAMPLE FIXED

We confirm fixture on the following terms:

VESSEL: MV EXAMPLE
LOAD: Shanghai, CW 33-34, 2026
DISCHARGE: Rotterdam
CARGO: 32,000 MT steel coils
FREIGHT: $18.00/MT = $576,000
PAYMENT: 50% on B/L, 50% on arrival
LAYTIME: 5 running days loading, 5 running days discharging
DEMURRAGE: $3,500 per day
DISPATCH: 50%
GENERAL CONDITIONS: GENCON 94

Please confirm your acceptance.

────────────────────────────────

DAY 1, 15:30 — CONFIRMATION OF THE RECAP

From: Owner's Broker
To: Charterer's Broker
Subject: RECAP CONFIRMATION

We confirm your recap dated 01 August 2026 with reference MV EXAMPLE.

All terms as per your recap accepted.

Fixture confirmed.

────────────────────────────────

DAY 2, 09:00 — SIGNING OF THE CHARTER PARTY

[Both parties receive the signed document]

Practical advice for a chartering specialist

What to do

What not to do

Freight calculation: examples

Example 1. Voyage charter

GIVEN:
- Vessel: General Cargo, 35,000 MT DWT
- Freight rate: $50/MT
- Cargo: Steel products, 28,000 MT
- Laytime: 5 days at 1,000 MT/day = 28 days
- Actual work: 35 days
- Demurrage: $3,500/day

CALCULATION:
1. Base freight = 28,000 MT × $50 = $1,400,000

2. Demurrage:
   - Excess days: 35 − 28 = 7 days
   - Demurrage = 7 × $3,500 = $24,500

3. Final freight:
   Total = $1,400,000 + $24,500 = $1,424,500

PAYMENT TERMS:
- 50% = $712,250 (on signing B/L)
- 50% = $712,250 (on arrival at the port)

Example 2. Time charter

GIVEN:
- Vessel: Tanker, 130,000 MT
- Daily rate: $48,000/day
- Period: 6 months ≈ 180 days
- Delivery: 1 September 2026
- Redelivery: 28 February 2027
- Off-hire events: 8 days of breakdown

CALCULATION:
1. Base hire:
   - Number of days: 1 September — 28 February = 180 days
   - Daily rate: $48,000
   - Base hire = 180 × $48,000 = $8,640,000

2. Off-hire (deductible):
   - Days without payment: 8 days × $48,000 = $384,000

3. Final hire:
   Total = $8,640,000 − $384,000 = $8,256,000

PAYMENT TERMS:
- Monthly in advance: 30 × $48,000 = $1,440,000/month
- For 6 months: 6 × $1,440,000 = $8,640,000
- After deducting off-hire: $8,256,000

Example 3. Container charter

GIVEN:
- Vessel: 5,400 TEU
- Rate: $1,200/TEU
- Cargo: 4,000 full containers (20-ft)
  + 200 reefer containers (within the 4,000)
  + 400 empty containers for repositioning
- Reefer surcharge: +15%

CALCULATION:
1. Standard containers:
   - (4,000 − 200 reefer) × $1,200 = 3,800 × $1,200 = $4,560,000

2. Reefer containers:
   - 200 × $1,200 × 1.15 = 200 × $1,380 = $276,000

3. Empty containers:
   - 400 × $200 = $80,000

4. Final freight:
   Total = $4,560,000 + $276,000 + $80,000 = $4,916,000

PAYMENT TERMS:
- Advance payment (25%): $1,229,000
- Balance (75%): $3,687,000
- Payment within 10 days of B/L